Home

About Us
  2/5 Tooth Street, Mitchell ACT, Australia


                    Kitchen Renovation Advice
Location Map
Five steps to a perfect Kitchen About Costs & Quotations About Design & Choices Photo Gallery & styles. Kitchen Accessories Other useful sites
Five steps - quick overview About Appliances About Schedules Choosing a Designer About Colours Accessories

Before you start .........

Calculator.gif

So you spent months contemplating, designing and re-designing your new kitchen. You have thought about everything from the colour of the kickboards to the location of the handles and now your ready to sign on the dotted line to get the manufacturing started. You are all eager and keen and by know you just want the kitchen in, you've waited already long enough.

Installation of your new kitchen may be far from instant once you have placed your order. Some products and materials that need to be bought-in may require long lead times of between two to six weeks and the kitchen can't have even begun to have been installed until these materials have arrived.

"Each new kitchen sold may require from 10-20 Purchase Orders."

Even when obtained off-the-shelf components often have to be cut up, edged, drilled and machined then fitted in the factory, before they can be installed in your home.

A typical custom kitchen is usually installed anywhere from 4 weeks from signed contract (usually the earliest) to 12 weeks (usually the latest).

That does not mean that as soon as the contract is signed the workmen arrive and rip out the old kitchen and that then your are without a kitchen for 4 - 12 weeks! No - the kitchen is designed, then manufactured and assembled in the workshop, and the removal of your existing kitchen is synchronised with the actual installation of the cabinetry.

Typically the cabinetry is removed on day one, the Plumber and Electrician get their side of alterations partly installed and the next day the kitchen installation begins (sometimes it is on the same day as the removal).

Your job upon contract signing will be scheduled into the "Installation Project Planner" and in our "MS OutLook" daily diary. A final site measure is usually required by the Production manager to verify that all last minute design changes still fit within the physical boundaries, and that has to be booked in.

Then the entire cutting lists has to be planned from start to finish, all of the bought-in materials need to be ordered and others need to be validated that they are in stock and not used by prior jobs. Each new kitchen sold may generate from 10-20 Purchase Orders.

After that there is the wait for the materials need to arrive at the factory, some materials take a day, others take up to four weeks (lacquered solid timber doors for example). Once all the materials turn up then the job needs to be slotted into the next available spot in the manufacturing cycle, after which Your job is cut out, edged, drilled and machined, then assembled and cleaned and stacked ready to be delivered.

All this is pre-planned and we expect that barring major catastrophes, when your date of installation arrives that your kitchen is fully assembled and ready for shipment so the installation process can commence.

To get it to this stage requires a lot of logistical work behind the scenes by the Production Manager, but it's not over yet.
"Glass splashbacks may have a long schedule."

The installation crew arrive after the Plumber and Electrician have been and the cabinets are installed. This process will be finished quickly, but it depends a bit on the materials that you have selected.

If you selected a laminated bench top and a tiled splashback then the bench top is usually finished off at the same time as the cabinets are installed, and the Plasterer follows the next day and the Tiler on the third day - they will return the next working day for sanding and grouting.

If however, you have selected a granite bench top and glass splashback with an appliance cabinet on the bench top (for example), then after the cabinets have been installed the stone mason has to arrive to create a site template for the job, then he has to schedule your job into his work schedule. Usually the stone mason returns after 8 working days with the granite bench top and starts installation, he is usually there for the full day. Then the Plumber has to return to connect the sink, and the Kitchen Company returns to install the appliance cabinet.

Glass splashbacks may have a long schedule. The Glazier normally arrives after the benchtop is installed to template for the glass splashback. Because it is toughened glass which is painted on the rear, this gets done in Sydney and can take from 2 weeks to 4 weeks (depending upon how busy the glaziers are). Once the glass is shipped back to Canberra, then the glass splashback is then scheduled into the glaziers work schedule to be installed in your home. After the glass is installed you can't use the kitchen bench tops until the next day so that the silicone has had time to set.

So a quick calculation from the time the cabinets went in to the time the Glazier has finished the glass splashback shows that your kitchen sink may be out of action for four weeks longer then having a laminated bench top with tiles as a splashback.
Not only that but the Granite and the Glass Splashback would have probably set you back about an extra $5,000 more in cost!
Now if you were to have structural building work as well you could well add another week to two weeks on top of that.

Thus it is very important when selecting your kitchen finishes, that you realise that some products will take longer to complete than others and you cannot expect that just because they cost more that they will be installed faster. More often than not this is not the case.

"a good designer will help you do the job right the first time" During this long finishing time the kitchen will seem to go through many days without a workman showing up, it's not a fault in the production scheduling, rather just that actual time that is required to manufacture certain products and that many processes are dependent on the completion of prior tasks

Here's an example installation schedule, to be used as a basic guide only

Work To Be Done Time To Complete
Structural changes (i.e. knocking out a wall, installing a sliding cavity door, installing a new window, removing a load-bearing wall) 2 Working days to a week
Old kitchen's cabinets, appliances, and other features removed, electrical wiring and plumbing disconnected and pipes and electrical relocated ready for new kitchen; 1/2 to 1 Working day
Kitchen cabinets delivered and installed 1-1.5 Working days
Electrician & Plumber return to connect up power, lights, plumbing and finish Off 1 Working day 
Plastering work 1 Working day
Tiler 1.5 Working days
Quality control (if required) check, final adjustments  1 Working days
Add on: Granite / Rocksolid / Corian / Stainless Steel bench tops 8-10 Working days:
Note: these last three items , if required can be overlapped.
Add on: Glass Splashbacks 3 - 4 Weeks
Add on: Flooring & Painting (if Required) 1 -1.5 Weeks

The Modern Kitchen Designer:

From the foregoing discussion is it clear that the kitchen designer has to work in closely with the manufacturer, installer and other Trades people to ensure that suggested materials and products are available in a reasonable time period.
Most kitchen Designers today typically operate with well equipped showrooms, close to or allied with the manufacturing premises and in close contact with other team members in the field (Production controller, factory manager, purchasing clerk, other trades people, etc).
Some have begun their trade as a Cabinetmakers and have shown flair for design and organisation and progressed to become Kitchen Designers, while others have been trained more broadly as interior designers, then adapting their skills and flair with colour, light and space successfully to kitchen designs. 
Others still have had neither a Trade or Interior Design background and have learnt as they went along. 

Some have also received the designation of Certified Kitchen Designer CKD(Aust.) from the National Kitchen and Bathroom Association.
While such qualifications are not mandatory for designing kitchens, the CKD designation requires the passing of a theory examination and a minimum set amount of years full-time professional experience designing kitchens.  This is the highest credential that the Industry has and anyone that is a CDK is a qualified and respected professional in this Industry.

A designer, apart from developing innovative designs and detailed specifications, can pull all the tasks of your kitchen project together. The designer will keep you from getting bogged down in details that can throw your planning off track. You'll be free to dream, while the designer thinks through all the measurements, material coordination, and construction logistics that will make your dream a reality.

In other words, a good designer will help you do it right the first time, see possibilities where you could not, and make the entire experience go smoothly.

When you work with a kitchen designer, you don't have to give up control of your plans or turn all the remodeling work over to other craftsmen. Think of yourself as the project director and of the kitchen designer as the project manager. You can be intimately involved in every detail of the project and even do some of the hands-on work. But when you do need someone to handle logistics, whether it's ordering products or coordinating contractors' schedules, the designer or her/his colleagues can step in

The designer will:

bullet2.gif     Visit your home to take measurements.
bullet2.gif      Create a the design perspectives, elevations and floor plan.
bullet2.gif      Develop a detailed quotation.
bullet2.gif      Discuss the design reasons with you and apply modifications.
bullet2.gif      Assist with colour and materials options.
bullet2.gif      Review modifications to meet changing requirements.
bullet2.gif      Formalises agreed plans and specifications into a contract.
bullet2.gif      Schedule your job into the production.
bullet2.gif      Assist in coordinating of plumbing, etc. contractors.
bullet2.gif      Oversee the construction and installation of all design elements.

Be sure to clarify up front though, who will be responsible for the sub-contractors. Some design firms will coordinate the contractors' work only after you have selected and come to separate agreement with each sub-contractor. 
Aneka Kitchens however, prefers to contract the Plumber, Electrician and other sub-contractors that they have quoted for, to ensure all the work is carried out on schedule and that the work is carried out as per contract


Contact Information

Telephone -  02 6241 7778 (Answering machine switched on at 4.00pm week days)

Fax -  02 6241 8068

Postal & Showroom Address - Unit 2 / 5 Tooth Street, Mitchell  ACT  2911 Canberra, Australia

Send us an e-mail to book an appointment, or to ask for more details or even to express your comments about this website - we are open to suggestions -

    aneka@aneka.com.au

[ to Top of page ]  


Home

About Us
  2/5 Tooth Street, Mitchell ACT, Australia


                    Kitchen Renovation Advice
Location Map
Five steps to a perfect Kitchen About Costs & Quotations About Design & Choices Photo Gallery & styles. Kitchen Accessories Oher useful sites
Five steps - quick overview About Appliances About Schedules Choosing a Designer About Colours Accessories

Aneka Kitchens : Scheduling.html

created by Henk Thijssens, Custom Design and Administration (CDAS)
Kitchen design processes and ideas,

last modified: 20 November, 2003